BOONE, Iowa---In December, the Boone City Council was given a tentative time frame for the progress on the northeast Boone Sanitary Sewer Rehabilitation Project.  Expectations were that plans would be done over January into February.  Bids would be taken in March and work could begin in April or May.  The northeast Boone project will include the lining of several blocks of sewer line, some possible digging for new line and numerous manhole replacements.  The City Council is hoping to here good news in March about being awarded a Community Development Block Grant.