Monday, June 6, 2011

Demolition of District Buildings Underway

BOONE, Iowa---Contractors began of process of demolishing two vacant elementary buildings last week. Boone School Superintendent Brad Manard says he expects the work will go quickly. Environmental contractors are handling the asbestos abatement. Two contracts were were approved, Lindstrom Environmental from Plymouth, Minnesota is working at the Lowell building and R-E-W Services is handling the Bryant building. Actually demolition will be handled by Anderson Excavating of Omaha. Anderson Excavating handled the demolition of the fire damaged buildings in downtown Boone in 2010.